Welcome to the 2025 Road Project Page
This page will keep the residents of Fountain Lake up-to-date on all the phases of our upcoming road project. Come back often to get updates and the latest status. Any questions about the project, please send an email to flra_bod@yahoo.com.
Status:
24-March: Road Project FINISHES
11-March: Phase 2 of roadwork starts
28-Feb: Phase 1 of roadwork starts
26-Feb: Non-Roadwork completed (150 feet of sidewalk, 2 drains, concrete retaining wall under upper pool deck
10-Feb: Construction Start
01-Feb: The Project Overview has been loaded as well as the link to the Site Map. contract signed with Nelson & Nelson Concrete